Ashfield

Project Stages
Centurion Framing Systems partnered with Trio Homes to deliver steel wall framing and roof trusses for a five-unit residential development in Ashfield.
The project highlights the speed and efficiency of prefabricated steel framing, with all five units framed within just four weeks, supporting rapid construction while maintaining consistent quality across every dwelling.
Project Details
Project Size
Five-unit residential development
Project Timeline
Commenced: July 2026
Completed: August 2026
Project Highlights
- ⭐ Five units framed in four weeks
- Multi-unit development
- Fast installation
- Precision manufactured
The Challenge
Five units on one site means five sets of frames arriving, being stored and being installed in the right order without the site turning into a materials yard. Any variation between units compounds through every trade that follows. The other challenge was the external brick work was being installed around the same time as roof frames install, proving a co-ordinated solution was needed between Centurion, the builder and the trades.
Our Solution
Centurion manufactured the wall frames and roof trusses for all five units to identical engineered specifications and delivered them in installation sequence, so each unit could be framed and closed in progressively rather than all at once.
What This Meant for the Builder
All five units framed within four weeks, with the same tolerances across every dwelling and no rework between units.