Glendalough
Project Stages
Centurion Framing Systems supplied the steel framing package for Stage One of a medium-density residential development in Glendalough.
The project demonstrates the capability of steel framing for larger residential developments requiring consistent quality across multiple dwellings and efficient construction sequencing.
Project Details
Project Size
33 dwellings in the phase 1 & 2
Project Timeline
Commenced: April 2025
Completed: July 2026
Project Highlights
- Phase One -15 townhouses completed
- Medium-density housing
- Precision engineered
- Delivered on schedule
The Challenge
Medium-density sites demand accuracy. With dwellings sharing boundaries and services, and very little room to store or sort materials, there is no tolerance for out-of-square framing or for a package arriving in the wrong order.
Our Solution
Centurion engineered and prefabricated the full framing package for Stage One offsite, delivering it in installation sequence so each dwelling could be framed and closed in before the next began. Precision-rolled steel components held consistent dimensions across every dwelling in the stage.
Detailed Services Provided
- The first stage of townhouses was handed over in July 2026 with Centurion continuing to deliver across Stages 2 and 3 of the development.
What This Meant for the Builder
Repeatable framing across the stage, minimal onsite storage, and no rectification for material that warps, twists or shrinks.